Thursday, September 20, 2012

22 August 2012



Following are Minutes for the Cloverleaf Center Condominium Board of Directors Meeting held 22 August, 2012, in Conference Room A, Upcounty Regional Services Center, Germantown, MD 20874.

Farouk Youssef called the meeting to order at 7:05 PM. Mr. Youssef received Kreg Williams’ written proxy for this meeting.  Andrew Kim and Peter Franke were present. Noorul Hinaya Jainoor is expected to arrive later [Ms. Jainoor arrived at 7:45 PM during the discussion of the County easement, see below.]. This meeting—delayed from the third Wednesday of August—was announced by a special postcard and by the sign. A motion (FY/PF) was made to close the Meeting at 8:30 to discuss WTP & delinquencies (Vote: 4 Aye/0 Nay.) Motion (FY/PF) to approve the May 16, June 20, and July 18, 2012 Minutes (Vote: 4/0.)

Continuing Business and Management Report

Elan Krueger (Management) reported that letters were sent yesterday calling for candidates for the four Board positions (two Plex and two Town House positions) that will be open in October, and announcing that the Annual Meeting will be held on Wednesday, October 24, at 7 PM, Conference Room A. Management sent a letter to 13015B regarding a satellite dish, as the wire may not penetrate the building and may not be tucked into the siding or trim. That issue has been resolved.  Letters were sent to four owners for Contractor access to their units to pull the sliders, in order to apply flashing. The four owners were all present at the time requested. Some discrepancies were noted during the Quarterly fire alarm inspection, but we have not received a proposal for fixes, yet, and have not seen any life safety issues. An advance draft budget was sent to the Board for review. It assumes no fixed contract for snow. [Later in the meeting, Mr. Krueger announced that Bridget (Brickman) will accept a fixed contract for snow removal at $12,000. Audience response was highly favorable. See below.] The draft proposal also asks for no increase in Management fees, as last year’s—from July 1, 2011 to June 30, 2012—inflation rate was about 1.4%. The Auditor was confused about the schedule for the field work, which is now scheduled for Sept 5. We requested that the Auditor send the Draft at least three days before the September 19 meeting. The next Audit Engagement Letter will specify sending the Draft before the March Board meeting, as the loan documents require that the Audits be submitted to the Bank within 120 days of the end of the fiscal year (Dec 1.) The WTP Collections printout and the July 31 Financial Statement were sent to the Board for review. The MD Court of Appeals “Pit Bull Decision”, briefly, is that anyone who has control over the presence of dogs has an absolute liability over a pit bull attack. Thus, by association, a Condominium can be liable. Various attorneys are talking to us about this, saying to muzzle the dogs, to grandfather existing dogs, and to shift the burden of proof to hold the owners liable. The Insurance Industry is behind on this and our insurance will cover this for now, but that could change overnight. Attempts were made to talk with Direct TV and with Dish Network [an owner noted that the satellite TV providers offer otherwise unavailable international stations]—in order to inform these providers that the Association owns the Plex buildings and the grounds, and that the Board requires written approval prior to their touching the building—but these attempts have been refused. Management therefore recommends sending a card to each owner to inform them that the Board requires ACC approval before installing a dish, regardless whether the Board can notify the provider companies.

Mr. Youssef, speaking about the Plex Project, announced that each Plex owner will need to provide inside access so the Contractor can remove the sliders and add the flashing. About every 15 days, the President, Treasurer, Manager, Engineer and Contractor have held progress meetings. Last Thursday, the Contractor stated that the reason that “Bldg 2” has not yet been finished is that there has been extreme difficulty gaining inside access to perform these changes. The side of Bldg 2 on Bridger Dr is about finished, but the back side looks like a horror show. Nevertheless, Bldg 2 will be finished and closed within 15 days.  To advance the project to an end on Oct 15, the Contractor has been opening the other buildings, and to date all of the decks have been shored with brackets and hangers. When the time comes to remove the sliders and windows, the remaining work will go fast. Mr. Youssef asks that the people in the remaining buildings be aware of that on short notice, we will ask to be let into the unit. [An owner commented that during the installation of a new slider, the measurement was short and a panel to the slide plate needed to be removed.] [Another owner mentioned pop-up nails.] Mr. Youssef replied that as the Contractor has previously written in a letter to the community, nail pops are expected; when the owner hammers in any pop-up nails, it is better to seal them. Other mishaps will be taken care of. Finally, the Engineer found some excess in the prices of some items, and we will be able to save about $30,000.

Mr. Youssef opened the floor for any other audience questions regarding the project. “Will you remove rotted wood under the slider?” (Yes.) “Is replacement of a French door mandatory?” (No.) (In some cases, in spite of the care of the Contractor, a door, because of its age, may be unusable after removal. In that circumstance, the owner pays for it.) (Owners will get a letter about 72 hours ahead of time to notify them when they will need to be available for the Contractor to enter into their units.) (The Contractor will try to schedule the work by tier (utility stack),so as to avoid moving the scaffolding back and forth.) “I cannot now open the utility door, and there is still a gap by the edge of the deck.” (The Engineer will look into this, as the shoring cannot be removed without the approval of the Engineer.) (The subflooring cannot be leaked into after the repair, so you won’t need to change that.)

The Board previously voted to delay the payment of WTP legal fees for collections for sixty days, but that didn’t work. The problem is that WTP has not yet fought to collect the legal fees—which the Association has paid-for, up-front, without delay, to WTP—after collecting delinquencies. That is not acceptable to us. In one example, a case resulted in garnishment of wages. Why did not WTP collect by garnishment the legal costs of collection? We will put a stop to that. A motion was made (FY/PF) to pay WTP their fees upon written approval of the Board. Vote: 4/0.

Easement Update: A year and a half ago a County representative (Dennis Robinson) unexpectedly broke off negotiations that they had initiated with Cloverleaf Century Condominium regarding a request for a temporary lease of some of the Association’s property, for the purpose of installing carbon filters (on County land) to remove pollution from drainage from Fr Hurley Blvd, a part of the plan to extend Century Blvd to Kinster Dr. The County cited at the time lack of developer funds. The Association, by a vote of the Directors, accepted that offer, pending then-Director Diane Smith’s and the County Forester’s choice of tree and shrub species for planting a barrier strip near the edge of Cloverleaf’s and Cloverleaf III’s property. At the time, the County had rejected as “too expensive” Cloverleaf’s suggestion for a structural sound barrier. After an eighteen month lull, the County has now made a new, unexpected offer. The previous offer was $6000 for an 18 month lease. The new offer was $6000 for a ten year lease, without provision for a planted barrier. That is unacceptable.

 In a related development, Directors FY, PF and KW note that County representatives were present at (or supervising) a massive earth-works project that has occurred adjacent to the end of Kinster Dr in Cloverleaf II, eastward toward the 270 SW exit, NW toward the edge of the golf driving range, and SW to the edge of the riparian forest, deer, fox, frogs, old growth oaks, and other natural habitat that is the current border of Cloverleaf and Cloverleaf III. A surface water collection basin—now partially filled with water from recent rains—has been created near the Cloverleaf II edge of the forest. There was a small sign at the end of Kinster Dr indicating that the re-grading project is to improve drainage. We note that this means that drainage was not in conformity with EPA rules. We note that the resurfacing may be to accommodate an office building, and the procession of dump-trucks involved in the re-grading has already heavily impacted the formerly quiet flow of traffic on Crystal Rock Dr to Kinster Dr.  We note that altering the drainage may affect the Condominium’s insurance risk, should the resurfacing of the former drainage pond and flood plain make any part of Cloverleaf or Cloverleaf III more vulnerable on the 100-year flood plain map. We note that for the past five years there has been testing of the soil to see if it is solid enough for a road, and that these tests have failed every time. Finally, we note that noise impact studies anticipate that there will be unacceptable levels of noise at certain locations within our community. We therefore ask: What are the County and the developer hiding, and why have they not informed our community representatives? [A member of the audience stated that a sign on 270S indicates that an office complex is coming soon.] FY and PF note that Cloverleaf III representative Larry Harris has said that he also received notification (not yet in writing) from the Mr. Robinson, and that he told Mr. Robinson that CCIIIC will not sign any agreement, nor accept their offer of money, without coordination with Cloverleaf. A motion was made (FY/AK) to draft a letter to the County Executive requesting that the Executive inform Cloverleaf Center Condominium what is happening in regard to the roads, buildings and drainage, and copies to our County Representative, State Delegate [identified by a member in the audience as Aruna Miller], and the County EPA (notification of the US EPA pending.) Vote: 5/0.

The Treasurer reported that various reserve bank accounts have been consolidated to separate the Reserve Fund from the Special Assessment Fund. The intention is that 57% of current reserves and future reserve contributions (the portion specified in the Reserve Study for items related to the repairs covered in the Plex project, such as roofs, siding, etc.) remain in Access National Bank (per the loan documents.) The remaining 43%, not related to the project, is at TD Bank. After the Sept 7 maturity of a CD at UB, the Treasurer recommends opening CDs of $50,000, the remainder as cash.

The Treasurer thanked Mr. Krueger for preparing the first draft of the 2013 budget.  The loan documents require the special assessment income and fund and the project expenses on the budget, and quarterly cash-based accounting statements. The extra cost for these statements will be a Plex special assessment expense. In addition to the $12,000 Brickman offer for fixed contract snow removal which Mr. Krueger arranged, the Board would like some competitive bids for the next annual audit (guaranteeing that the loan document conditions will be fulfilled,) collections, insurance, and other contracts. A meeting will be arranged at the earliest convenience with the new collections attorney at WTP, to discuss among other matters FHA approval (estimate this date 15.3% delinquency), the above mentioned need to collect the accumulated legal fees, and estimates of bad debt in 2013.

New Business and Community Forum

Motion (FY/PF) to pay Katchmark for Invoice #4, dated 6 Aug, 2012, and to submit same to the bank, in the amount of $111,971.62. Vote: 5/0. Motion (FY/PF) to pay SRG Invoice #7756, dated 31 July, 2012, in the amount of $15,758.90. Vote: 5/0. Motion (FY/PF) to authorize automatic payment of the next five loan payments to ANB (the interest only period.) Mr. Youssef noted that the Board intends, after January, to pay a large lump sum ($250-300K), and to pay about $18,000 monthly, rather than the minimum (about $14,000) P&I payments, in order to avoid a balloon payment at term. Our cash flow was examined by the bank prior to authorizing the loan. Mr. Franke cautioned the Board to anticipate any “ups and downs” in the future and to keep a large amount in reserve.

The Board received a letter from 12915B, written under the Unit owner’s company letterhead. The letter states that due to our negligence, the owner incurred damages, and asks for a new door, slider and paint. As soon as the Board knew of that Unit’s pattern of leakage, the Board addressed the problem, at a cost to the Association so far of about $10,000. Several Directors have examined the ceiling and found no water stain. The owner harassed them about the $25K Special Assessment as they tried to stop the cause of the complaints. It is now known that will not stop until the siding is changed. The slider, which shows internal water condensation due to its age, was not damaged by a leak, as claimed. The Board answers letters sent to the PO Box; a similar claim was recently rejected. Motion (FY/PF) to answer the letter and to refuse the claim. Vote: 5/0.

The Manager asked whether the Board will allow a tenant to operate a daycare business at 20513 GCD. Mr. Youssef responded that there is a licensed day care facility in another Unit, 20537 GCD, run by the tenant.  According to our rules, the owner must ask the Board for permission.  The owner of 20537 GCD wrote that the tenant living there has his permission to operate a day care facility on the premises. In this instance, the owner should have written to the Board to ask for permission. Mr. Youssef requested that Mr. Krueger take care of this. Now in the situation at 20513 GCD, a real estate agent called Mr. Krueger to say that a possible renter is interested in opening a day care center.  That situation is more complicated. The prior owner fell behind in the mortgage, and arrived at a compromise with the bank. The bank paid what the prior owner owed, and the prior owner is staying in the unit as a renter. Motion (FY/PF) not to approve this until we get in touch with the bank. Vote: 5/0.

Motion (PF/FY) to send letters to owners to notify them of Bylaws Art V, Section 14 (Restrictions on Use of Units), part (b), which states (in part): “Nothing shall be done or kept in any Unit or in the Common Elements which will increase the rate of insurance for the Condominium applicable for residential use without the prior written consent of the Board of Directors.” In one instance, a Unit owner did not ask the Board for permission prior to putting a water slide on the grounds.

Open discussion: An Plex Unit owner brought examples of boards with nails left on the ground during the construction, and said that a downspout was left lying across a pathway. (These issues will be addressed.) A Plex Unit owner asked that the branches of a tree be trimmed away from the roof, so as to stop an ant pathway; a TH unit owner asked that branches from a common element tree be trimmed away from his property. (Mr. Krueger pointed out that in the second case, by MD &English common law the encroaching branch is the responsibility of the Unit owner.) A TH owner asked for Association help regarding continued Verizon disruption of the landscaping. (Asked Management to look into the agreement by which the Board allows a utility easement to Verizon for FIOS.)

The meeting was closed to discuss collections, and adjourned at 9:20 PM.

Thursday, August 23, 2012

July 18 2012 BOD Meeting


Following are the Minutes for the Cloverleaf Center Condominium Board of Directors Meeting, July 18, 2012, Conference Room A, Upcounty Regional Services Center, Germantown, MD, 20874.

Farouk Youssef, President of the Association, called this regularly scheduled and announced meeting of the Board to order at 7:03 PM. The other Directors—Peter Franke, Andrew Kim, Kreg Williams, Hinaya Jainoor—were all present. Minutes for the June 20 meeting were not available and approval was postponed, pending availability. (Note: The May 16, 2012 minutes are also pending approval.)  An agenda for this meeting was not available, but the meeting was held on the following issues at hand.

Elan Krueger reported that the call for candidates will be sent 60 days prior to the Oct 24 Annual Meeting. Ballots and a reminder of the meeting will be sent 30 days prior. The ARC approved the proposal at 20608 DPD. Deck safety letters were sent to 13031 and 13035 B, and a patio storage violation letter to 20548 GCD. A response was sent to 13001 B regarding request for reimbursement for interior repairs.  An insurance claim at 13051 B was settled for about $9,612. A tenant claim at 12957 B was settled for about $8,065. A service request by 13100 B (CCIIIC) for a French drain is not the Association’s responsibility, as the owner’s property extends 4’ from building. Furthermore, the CCIIIC attorney’s opinion is that by common law, no Board has responsibility for runoff.  Management will check whether Brickman has identified the correct pine tree for removal. The fire alarm mother board in Plex phase 13 (“Building 1”) failed, and was replaced for about $2,400. Mr. Krueger asked that the Board grant blanket approval for replacement of the windows and doors and the labor prices from Katchmark.

Motion: The Board hereby gives blanket approval for the replacement of doors, windows and sliders, provided that the unit owner contracts directly for replacing such items. The styles of windows, doors and sliders described and illustrated in the July 9, 2012 Katchmark Proposal are architecturally acceptable for installation.  Approved 5 Aye, 0 Nay.

Motion to pay contractor for Revised Invoice # 3 (July 11, 2012) and to forward to ANB: Approved 5/0.

Motion to close meeting at 8:30 to discuss a payment plan request and a bankruptcy write-off : 5/0.

Motion to pay $218 for 12 months PO Box fee, due July 31: Approved 5/0.

Motion for Mr. Youssef and Mr. Williams to reopen negotiations with Dennis Robinson (Montgomery County) regarding leasing a portion of our property, as the County wants to move on their project in September (letter of July 11), in the midst of our own project: Approved 5/0.

Structura modifications to the contract deferred to executive session, to be held within about 10 days.

In open session, there were discussions of an iron fence (estimated at $10-14/ft), whether delinquent owners are now paying, removal of the dead pine tree, who will run for the new board, when gutters will be replaced, when the balconies will be done, and the balcony sliders.

The closed session discussed also the ANB account and executed contracts, and adjourned at 9 PM.

Note: Farouk Youssef, Peter Franke and Kreg Williams met at a public location on at 8 PM on Monday, July 30, for an emergency meeting of the Board concerning the request of the County to proceed with their project as early as September; Andrew Kim sent his regrets as he was unable to attend. The Board discussed the negotiation with the County, and an implied threat of eminent domain. A motion was made (FY/KW) and approved (3/0) to authorize hiring a lawyer to respond to and to obstruct any explicit threat of eminent domain.


June 20, 2012 BOD Meeting


Following are the Minutes for the Cloverleaf Center Condominium Board of Directors Meeting held June 20, 2012 in Conference Room A, Upcounty Regional Services Center, Germantown, MD, 20874. 

Farouk Youssef, President of the Association, called to order this regularly scheduled and announced meeting of the Board at 7:05 PM. Peter Franke, Andrew Kim, and Kreg Williams were present. Hinaya Jainoor arrived at 7:13 PM. The Manager was not available. 

Mr. Youssef noted that the doors and windows are the property of the Unit owners; the sliding doors must be removed, and if it must be replaced, the Owner must replace it. These buildings were built in 1994-97, and that is a long time ago. Steve Katchmark is here to speak later on the contractor’s proposal for replacing doors and windows. Kirby McCleary (SRG) is here and is also invited to speak later.

Mr. Franke asked to speak on several items of continuing business: There are several more instances of BBQs on Plex unit decks and patios; the 20608 DPP ACC request has been approved; and Condominium Bylaws, Chapter V, Section 14(k), states, in part: “…Any member who keeps or maintains any pet upon any portion of the Condominium shall indemnify and hold the Association, and each of its members free and harmless from any loss, claim or liability of any kind or character whatever arising by reason of keeping or maintaining such pet within the Condominium…”; additionally, our Rule 12 (June 3, 1997) states, in part: “…The law of the County addressing Animal Control and Humane Treatment is adopted as the principle of practice within the community…”  Summaries of these laws have been found at: http://www.montgomerycountymd.gov/poltmpl.asp?url=/content/POL/districts/MSB/animal/summarylaws.asp  

A motion was made (PF/KG) to approve the May 16, 2012 minutes. Mr. Youssef objected to a comment in new business, item III. g. Mr. Youssef stated that it is easy to claim that they did building 1. They did not pay for it and left it for another board to deal with the debt, the lawyers, etc.  The tough part was to address how to deal with the roofs, which a recent MIT study says are responsible for 68% of leaks. We did six roofs for $350K. We are now opening building 2 to do the job as it should be built. That was promised, and will be done. Let us hold up: 4/0. 

The ACC added the following condition for approval of the garage door replacement request from 20520 Bridger Way: “Solid white, no windows.”

A motion was made (FY/AK) to pay the SRG invoices #7589 and 7590 by July 10. Approved: 5 Aye, 0 Nay.

Motion (FY/AK) to reject the bill and threat for non-payment letter from 13001 B: Mr. Youssef noted that work will be torn up by the contractor, and that was said here before. Mr. Kim noted that the owner did this on his own, and the work was not life-threatening or an emergency. Approved: 5/0.

Mr. Youssef noted that we should have had the money for the loan in the bank last week, but the bank’s lawyer found a lien on the property [including the town house property and everyone’s personal property.] Mr. Youssef will take action for trespass, and those who signed will be called to task. The lien has been removed, and we have a bill. 

A motion was made to approve the “Minutes of Meeting of the Board of directors of Cloverleaf Center Condominium [sic]”). [In plain language: The Condominium is authorized to borrow $1.3MM pursuant to certain loan documents. The loan documents are approved. The President and Treasurer are authorized to execute those documents on behalf of the Condominium, and other actions they deem necessary or advisable.] Approved: 5 Aye, 0 Nay, 0 Abstentions. Five copies were signed, a copy for each Director.

The meeting opened for public discussion. Gratitude was expressed; a question about the wood door frames; a comment about paying even more; a question whether the town houses are implicated in the loan [no]; and the order of work. 

Mr. Katchmark was invited to give an update: The roofing, trim work, gutters are done. Started the siding and replacing the wood trim, and investigating the backs (rot, framing.)

Mr. McCleary then spoke. He became involved two years ago. It was a slow process to find out what is wrong and to do the bidding, and to wait for the Association to get financing.  He investigated several of the six buildings, and found occurrences of leaks, negative sheathing, and other joint problems. He stated that in the mid 1990’s, Code did not require a weather resistant barrier, and water will find a lapse. Wall to roof joints were also not flashed properly.  Other issues found: Leaks around the sliders; deterioration and separation; water infiltration and deterioration of deck attachments; wooden floor trusses, supported on end of well beds, should attach to the ledger board (in one case, in building 3, was split.) 

Now, we have a handle on the other balconies. We’ve opened 50% of them in building 2, and did not find that. In building 2, we did find a gap and slope, and found that it had dropped, and that the block at the corner had deteriorated, due to an important defect in the design. Today we found the same condition in the opposite deck. This is not just a siding project, and we have found some structural damage, so we’re doing spot structural repairs, removing some sheathing, adding weather protection, and window and door flashing. New siding and roofs were an issue, and the window and door options.

 [Question from floor whether we’re going to remove the sheathing?] Mr. McCleary answered for deck only. [Statement from floor that in building 1 there were three stories of rot] Mr. McCleary answered that it does not have that damage or indication.  Mr. Katchmark also answered that if it is in poor shape, we will replace it, and if the thermo-ply [sheathing] is buckled, we will replace it.

Mr. Katchmark added that ideally, we want to pull all the windows, and we can replace windows at reduced cost. Doors [sliders] will be removed and put back in: We will need the help of the owners so we can remove and replace them.

Public questions and answers continued: Cost to replace a slider (about $900); warped door [will address]; quality of windows, doors (upper medium grade, better than what is there, and energy efficient); warranties (offer 5 years workmanship); what to do with deck stack (clip and water proof); the doors of delinquents (yes, a problem); can all windows and doors be done in one day (yes)?

Mr. Kim stated to just email all your requests to cloverleafproject@katchmark.com. Public discussion then broke into individual conversations involving the owners with Mr. Katchmark and Mr. McCleary.

A brief closed meeting was held to discuss the current delinquencies.

The meeting adjourned at 9 PM.




May 16 2012 BOD Meeting


Board of Directors Meeting
May 16, 2012
Upcounty Regional Services Center, Room A
12900 Middlebrook Road, Germantown MD

I.                    Farouk Youssef called the meeting to order at 7:04 PM. FY, Peter Franke and Kreg Williams were present and constituted a quorum. (Andrew Kim arrived at 7:20 PM; Hinaya Jainoor was absent.) Meeting was announced by post card and sign. Motion (FY, PF) to read & approve minutes of April 18, 2012. Vote: 3 Aye, 0 Nay, 2 Abstain.
II.                  Continuing business and management report (Elan Krueger)
a.      Motion (FY, KW) to close meeting at 8:30 PM to discuss delinquencies and another legal matter. Vote: 3 Aye, 0 Nay, 2 Abstain. 
b.      FY reported on the construction and the loan; issue of gutters and downspouts; temporary repair work related to the project; inspection of concrete; ironwork:
                                                  i.      Since the roofs were finished faster than expected, we’re now in a lull.  That is a calamity for all of us, as the loan has not yet been approved, so we don’t have enough money to proceed to the next logical step (the siding and the balconies.)  The portion not yet done also includes new gutters & downspouts, and we don’t want to tear them out again when the siding is removed. That said, heavy rains caused some units to continue to leak, especially around the sliders.
                                                ii.      We have not been idle in this regard, and have promptly answered all questions from the bank about our cash-flow. For example, actual cash-based income is not reported in the accrual-method statements. To calculate cash income for the bank, we tabulated actual income listed on the monthly activity reports and arranged the data by class of ownership. For the period from January 2011 through March 2012, it took about 36 hours to reverse-engineer the reports to get a single value (cash income) for that period. Since the accountant could not get to that project in time, we did the work.
                                              iii.      We asked the bank for a date certain on the loan, explaining that if we are further delayed, we need to go ahead with the gutters, downspouts, and balconies. They explained that they cannot give us a date certain, and we asked what it is exactly that they want, so that there is no misinterpretation. The bank wants it simplified, and understands and mostly agrees with our statements of cash on hand.
                                               iv.      A now old, repeated problem is that the engineer did not know where the leaks are coming from. In one case, about a week ago, the engineer and his assistant located the source of a leak, at a cost of $6500. In another incidence, in “Bldg 2,” we’ll see how to remedy within two weeks.
                                                 v.      FY, EK and PF inspected concrete walkways and concluded the issue is not pressing right now. TH people own their lot so concrete is theirs; what is a concern are the walkways from one building to another.
                                               vi.      Found a trade person who has fixed the iron railings.
c.       Motion (PF/KW) to proceed at this time with drainage, tree replacement between TH Buildings 6 and 7 (behind 14 DPC). Vote: 4 Aye, 0 Nay, 1 Abstain.
d.      13055B ACC requests (AC, vent): The owner wrote on May 10, 2012 that: “…the current disconnect box can and will be reused since 1) it will not negatively impact the functioning of the new system and 2) the box does not need to be relocated.” The BOD approved the owner to remove a portion of the fence and reapproved erecting the ventilation pipe. FY underlined the instruction to not change or relocate the disconnect box from its current location and signed both requests.
e.      20608DPP ACC request (removal, replacement, realignment): Deferred decision pending a meeting at the site, and an examination.
f.        EK noted the Annual Meeting will be held on Wednesday, October 24, 2012. The meeting notice and call for candidates will be mailed in August.
g.      FHA. Motion.
III.                New business and community forum
a.      BBQs are prohibited on Plex decks and patios: EK sent 4 letters and 1 email to Plex unit owners notifying them that use or storage of BBQ grills on Plex decks or patios is against the rules and a violation of the Montgomery County Fire Code.
b.       Discussion of the “MD Pit bull Case”: The MD Court of Appeals has ruled that owners in multifamily housing are not allowed to keep that breed or mixed breed. FY stated that if this singles them out, that may constitute an illegal enforcement of law, and that the case may be put into the Federal Courts system. EK stated the case involved a pit bull in an apt building; the victim’s family sued everyone, including the apt building owner; the Court stated the breed is inherently dangerous, and allowing a pit bull is negligent and makes the building owner liable; the recommendation is if Association’s rules allow, to pass a rule to prohibit pit bulls and pit-bull cross breeds; insurance will not cover us if sued. Should such a rule apply to anyone who now owns a Pit bull breed, or hence forth? What now is the MD law on liability if an animal’s owner does not assume full liability? As other Condominium Associations may be asking similar questions, may we limit our Association’s portion for legal consultation of these matters to two hours, or however much is a fair share?
c.       Motion (PF/FY) to pay Structura Invoice #7511. Vote 4 Aye, 0 Nay, 1 Abstain.
d.      FY deferred discussion on drafting a binding resolution for repayment of a construction loan.
e.      PF noted that some new owners may not be paying their dues, or not paying consistently. To avoid this, and to give the benefit of the doubt, FY recommends a warning letter to those, stating that fees are due the first day of the month, a $15 late fee is applied after the 15th, and after 90 days the delinquency may be referred to the attorney for collection of assessments, legal fees, and legal interest. Discussion of recovery of legal fees for collections, warning letters.
f.        Received a letter, allegedly from 13001B, a form of threatening correspondence to pay or else. First, the letter is not dated or signed and is not a legal document. Second, we will not yield to threats. In the past, that owner was the first to receive an engineering study of a unit, as well as temporary repairs.  The work he has done will be redone in the project, and everything he has done will be destroyed. FY rejects the letter.
g.      Open discussion included the project, loan and Brickman landscaping.
                                                  i.      Anna Prisutti of 13009 B stated “At least we [the previous Board] succeeded in doing one building, but not the stuff not required, which was the roof."
IV.                Closed discussion and adjournment
a.      Discussed WTP cases and actions.


The ACC met in a special session at 20608DPP at 7 PM on May 24, 2012.
1.      AK, PF and MH (owner) were present. FY, KW & HNJ were unable to attend.
2.      Owner measured the areal dimensions (100”W and 72”D) of the proposed flagstones. This depth is slightly greater than the existing pavers & will displace a few inches of grass. Space between pavers will consist of a sand-gravel mixture.
3.       AK & PF found no objections & recommended approval of the proposal.


The BOD met in an emergency session at a public location at 7:45 PM on June 4, 2012 to discuss ANB’s approval of Cloverleaf’s request for a commercial term loan.
1.      The Executive Committee (FY, AK & PF) was present. KW & HNJ were unable to attend.
2.      FY moved to hire a competent attorney from WTP to execute the ANB loan documents until closing. Vote: 3 Aye, 0 Nay, 2 Abstentions by absence.
3.      AK volunteered to draft a binding resolution to direct repayment of the loan.
a.      Repayment is funded by the special assessment, as amended, and by 57% of the reserve fund.
b.      The BOD directs that no less than minimum required payments shall ever be made. The BOD authorizes payment of $18,000 or more per month, if possible, so as to pay off the loan during the term of the special assessment.
c.       Attach a copy of the executed June 4, 2012 commercial term loan letter.
4.      FY called S. Katchmark, who affirmed that downspouts will be removed and reattached with greatest care, and that gutters will not be touched during siding work.